The following is a list of items that are required to obtain a
Certificate of Occupancy:
Final Inspections
Please call the inspection line (954) 730-3060 when
scheduling inspections.
Subcontractors are responsible for calling in their inspections.
All related permits must be finalized prior to the General
Contractor scheduling their final C/O inspections.
C/O'S will not be issued on the same day that the inspections
are scheduled. They should be available within 24-48 hours after
the approval of final inspections.
Required Paperwork
- Building Department
- Soil treatment certificate
- Insulation certificate
- Health Certificate (If property has a Septic Tank
or is a Restaurant)
- Zoning Department (residential)
- Final survey
- Elevation Certificate
- Engineering Department (commercial)
- Final Survey |